February 2013 in Network Rail and Suppliers
Communication and teamwork
Method of working
Workload
Not Specified
Concerns have been raised that trains are being scheduled into the working timetable without being validated, potentially increasing the workload for Signallers.
February 2013 in Network Rail and Suppliers
Communication and teamwork
Knowledge Skills and experience
Signalling
South East
Concern has been raised about the procedure for briefing staff on the Autumn Working Arrangements at Marylebone signal box.
January 2013 in Network Rail and Suppliers
Communication and teamwork
Knowledge Skills and experience
Training and briefing
Supervision and Management
South East
A reporter is concerned about the use of apprentices and the mentoring provided to newly qualified Nominated Persons at Chadwell Heath depot.
November 2012 in Network Rail and Suppliers
Communication and teamwork
Knowledge Skills and experience
Method of working
North East
November 2012 in Network Rail and Suppliers
Communication and teamwork
Knowledge Skills and experience
Method of working
Rules and procedures
Central
A reporter would like clarification on the rules or procedures to be followed when engineering work requires staff to cross over the boundary between Network Rail (NR) and London Underground (LUL) infrastructure
November 2012 in Network Rail and Suppliers
Communication and teamwork
Training and briefing
Knowledge Skills and experience
South East
Concerns have been raised about the adequacy of the briefings and training for Signalling and Telecommunications (S&T) staff within Woking delivery unit.
May 2012 in Network Rail and Suppliers
Communication and teamwork
Security
Scotland
March 2012 in Network Rail and Suppliers
Rules and procedures
Method of working
Level Crossings
Communication and teamwork
Not Specified
A reporter is seeking clarification on whether Signallers should be adhering toRule Book module TS9 part 2.6. This section applies when Signallers have been informed that the road traffic lights at an Automatic Open Crossing Locally monitored (AOCL) or Automatic Barrier Crossing locally monitored (ABCL) have failed.
January 2011 in Network Rail and Suppliers
Rules and procedures
Method of working
Communication and teamwork
South East
A reporter believes the auditing process of the Network Rail supply chain is sometimes ineffective, especially in relation to engineering work associated with Road Rail Vehicles (RRVs) and On-Track Plant (OTP).
January 2011 in Network Rail and Suppliers
Training and briefing
Communication and teamwork
Not Specified
A reporter has contacted CIRAS with concerns about the safety culture impacting negatively on the working practices of a company called Railway Vehicle Engineers Ltd (RVEL) who maintain the Network Rail infrastructure maintenance vehicles.